COSVR710 Contribute to controlling work quantities and costs

Overview

"This standard is about contributing to the control of work quantities and costs by implementing works quantities and cost control systems, identifying opportunities and recommending ways to make cost savings, investigating any variations and agreeing and implementing corrective action in accordance with current organisational requirements which are equal to or exceed current statutory and legislative requirements This standard is for people working in the occupational area of construction site supervision which is defined as the supervision of multiple construction trades and disciplines and can be used by operatives, supervisors and managers"

Performance Criteria

You must be able to:

P1 contribute to your organisational requirements in relation to controlling work quantities and costs

P2 collect, evaluate and report work quantities and cost data in relation to at least three of the following:

2.1 materials

2.2 plant, machinery and equipment

2.3 workforce

2.4 sub-contractors

2.5 recorded works

2.6 programmes and schedules

P3 identify and report at least two of the following opportunities for cost savings to the people responsible:

3.1 waste reduction

3.2 resource management and logistics

3.3 applications of new technologies and materials

3.4 energy and utility management

3.5 receipt and use of materials

3.6 alternative sources and types of materials

3.7 alternative suppliers of labour, materials and equipment

3.8 document control and record keeping

3.9 alternative methods of work

P4 investigate any variations to work cost or quantities, record the outcomes and implement the appropriate corrective action with the people responsible in relation to one of the following:

4.1 restore progress in accordance with agreed programme

4.2 agree new completion dates

4.3 identify potential variation

4.4 secure additional resources

4.5 alter planned work"

Knowledge and Understanding

You need to know and understand:

Performance Criteria 1

Implement systems to control works quantities and costs

K1 how to implement systems to control work quantities and costs according to organisational requirements in relation to:

K1.1 accurate take-off schedules

K1.2 organisational waste targets

K1.3 recording receipt, usage and wastage of materials

K1.4 on and off hirer of tools and equipment

K1.5 use of consumables

K1.6 transport

K2 how to use the systems implemented to provide early indication warnings of potential issues

Performance Criteria 2 Collect quantity and cost data

K3 how to collect and record work quantities and cost data relating to:

K3.1 materials

K3.2 plant, machinery and equipment

K3.3 workforce

K3.4 sub-contractors

K3.5 recorded works

K3.6 programmes and schedules

K4 how to report work quantities and cost data to people who need it in time to be able to use it

K5 why you need to collect and record work quantities and cost data

Performance Criteria 3 Identify opportunities for cost savings

K6 how to identify and report opportunities for cost savings relating to:

K6.1 waste reduction

K6.2 resource management and logistics

K6.3 applications of new technologies and materials

K6.4 energy and utility management

K6.5 receipt and use of materials

K6.6 alternative sources and types of materials

K6.7 alternative suppliers of labour, materials and equipment

K6.8 document control and record keeping

K6.9 alternative methods of work

Performance Criteria 4 Review variations and implement corrective action

K7 how to review variations in works quantities and costs

K8 how to agree and implement the following appropriate corrective action with the people responsible:

Corrective action

8.1 restore progress in accordance with agreed programme

K8.2 agree new completion dates

K8.3 identify potential variation

K8.4 secure additional resources

K8.5 alter planned work

People responsible

K8.6 the client, customer or their representative

K8.7 contractors

K8.8 consultants

K8.9 sub-contractors

K8.10 suppliers

K8.11 workforce

K8.12 internal management