This standard is about interpreting information to determine progress of the work, recognising materials, components and equipment used with the work, implementing actions to progress with the work and performing a supervisory role within craft and operative work areas as associated with work carried out in the built environment
This standard is for people working in the occupational area of occupational work supervision and can be used by supervisors and managers.
Performance Criteria
You must be able to:
P1 monitor progress of planned programme against the work schedules P2 identify inappropriate specified resources, record and report and suggest suitable alternative resources P3 identify and quantify any deviations from planned progress which have occurred, or may occur, and which could alter the programme P4 confirm the circumstances of any deviations, seek advice and implement appropriate corrective action P5 identify and report options which are likely to help the contract progress P6 report progress, changes to the operational programme and resource needs
Knowledge and Understanding
You need to know and understand:
Performance Criteria 1
Monitor progress K1 how to source information from the work schedule K2 how to monitor and report the progress of the planned programme
Performance Criteria 2
Monitoring resources K3 how to identify, record and report inadequate and inappropriate specified resources and suggest alternatives K4 how to identify the need for alternative resources K5 how to specify alternative resources
Performance Criteria 3
Deviation in progress K6 how to identify and record any deviations from planned progress which could alter the programme K7 how to quantify any deviations from planned progress Performance Criteria 4 Corrective actions K8 how to record and report the circumstances of any deviations K9 how to seek advice and implement corrective action in circumstances of any deviations
Performance Criteria 5
Identify options K10 how to identify, record and report options which are most likely to help the contract progress
Performance Criteria 6
Decisions and actions K11 when to report progress, any changes to the operational programme and any resource needs
*IMPORTED UNIT*
COSVR215 Monitor progress against work schedules
Overview
This standard is about interpreting information to determine progress of the work, recognising materials, components and equipment used with the work, implementing actions to progress with the work and performing a supervisory role within craft and operative work areas as associated with work carried out in the built environment
This standard is for people working in the occupational area of occupational work supervision and can be used by supervisors and managers.
Performance Criteria
You must be able to:
P1 monitor progress of planned programme against the work schedules
P2 identify inappropriate specified resources, record and report and suggest suitable alternative resources
P3 identify and quantify any deviations from planned progress which have occurred, or may occur, and which could alter the programme
P4 confirm the circumstances of any deviations, seek advice and implement appropriate corrective action
P5 identify and report options which are likely to help the contract progress
P6 report progress, changes to the operational programme and resource needs
Knowledge and Understanding
You need to know and understand:
Performance Criteria 1
Monitor progress
K1 how to source information from the work schedule
K2 how to monitor and report the progress of the planned programme
Performance Criteria 2
Monitoring resources
K3 how to identify, record and report inadequate and inappropriate
specified resources and suggest alternatives
K4 how to identify the need for alternative resources
K5 how to specify alternative resources
Performance Criteria 3
Deviation in progress
K6 how to identify and record any deviations from planned progress
which could alter the programme
K7 how to quantify any deviations from planned progress
Performance Criteria 4
Corrective actions
K8 how to record and report the circumstances of any deviations
K9 how to seek advice and implement corrective action in
circumstances of any deviations
Performance Criteria 5
Identify options
K10 how to identify, record and report options which are most likely to
help the contract progress
Performance Criteria 6
Decisions and actions
K11 when to report progress, any changes to the operational
programme and any resource needs